What is Risk and Why Manage It?
Every project, programme and portfolio operates under uncertainty. Risk is the effect of uncertainty on objectives. Effects may be adverse, favourable or both. An individual risk describes a particular uncertain event or condition; overall risk describes the combined effect of uncertainty on objectives, including interactions and uncertainty not readily expressed as individual events. Risk management comprises coordinated activities to understand, assess and respond to that uncertainty.
Understand
Every project, programme and portfolio operates under uncertainty. Risk is the effect of uncertainty on objectives. Effects may be adverse, favourable or both. An individual risk describes a particular uncertain event or condition; overall risk describes the combined effect of uncertainty on objectives, including interactions and uncertainty not readily expressed as individual events. Risk management comprises coordinated activities to understand, assess and respond to that uncertainty.
For an event-based risk, a cause, uncertain event and consequence can provide a clear description. For example: Because concealed structural conditions have not been verified (cause), additional deterioration may be discovered during refurbishment (event), potentially increasing repair costs and delaying completion (effects). This format is useful, but does not adequately describe every form of uncertainty.
Risk management supports realistic commitments, informed choices, timely escalation and opportunities to improve outcomes. It cannot eliminate all uncertainty or guarantee success.
Apply
A practical, iterative approach is to: (1) establish objectives, context and an appropriate approach; (2) identify uncertainty; (3) assess its significance; (4) select responses to threats and opportunities based on effects, options, costs and decision authority; (5) implement actions with clear ownership; and (6) monitor and review changing exposure and effectiveness. Communication, consultation and recording support every activity. This is a SimpliPM explanatory cycle, not a mandated framework sequence.
Worked example (RSK-EX-001): A bridge-refurbishment team must decide whether to commit to a repair approach before concealed structural conditions are verified. Available evidence includes historic inspection records and preliminary engineering advice; missing evidence concerns the extent of deterioration. Options are to proceed with explicit assumptions and contingency, undertake targeted investigation, or stage the works. An illustrative decision is to undertake targeted investigation before finalising the approach because potential disruption is material relative to investigation effort. The project manager coordinates the decision with competent technical specialists; survey findings and changes to access or scope trigger reassessment. This example is illustrative, not technical advice for an actual asset.
RSK-EX-001 · Concealed structural deterioration · Owner 11.01.03For straightforward work, a short discussion and concise record may be adequate. High-consequence or regulated work may require specialist methods irrespective of budget.
Explore
Managing each recorded risk independently may overlook common causes and combined exposure. For example, multiple suppliers relying on one transport corridor may create correlated schedule risk. Risk management should begin when objectives and choices are being shaped, not only after the plan is approved.
Key takeaway: Manage uncertainty to improve decisions, not simply to maintain a register.
Connected resources
Professional heritage: refer to controlled source register. SimpliPM explanatory synthesis is not an endorsement or verbatim reproduction of an external standard.
Connected explanations, guidance and tools
Further planned subjects and tools
- deep-dive: 11.02 — not yet available
- deep-dive: 11.03 — not yet available
- deep-dive: 11.10 — not yet available
- optional-tool: RSK-T01 — not yet available
Sources and professional heritage
Source information and verification are recorded by the content owner. SimpliPM guidance does not replace official requirements.
- APM Body of Knowledge, 8th edition (opens in a new tab)
Verified APM eighth edition publication listing; relevant chapter/section content not accessed.
- What is risk management? (opens in a new tab)
Verified public APM page; individual/overall risk, threats/opportunities and cause-event-effect supported.
- ISO 31000:2018 Risk management — Guidelines (opens in a new tab)
Verified published ISO 31000:2018, edition 2; overview confirms principles, framework, process, threats/opportunities. Full clause check not performed.
- Risk Management in Portfolios, Programs, and Projects: A Practice Guide (opens in a new tab)
Verified PMI September 2024 practice guide title, scope, date; detailed text not accessed.